projects > Wolverine Underground Mining Development Project
Wolverine Underground Mining Development Project
Yukon Zinc Corp.
YUKON TERRITORY
START-UP: March 2005
COMPLETION:
ongoing
RESOURCE:
Lat 61° 9’ N – Long 130° 44’ W
RESOURCE: Zinc
Procon has been at the Wolverine Mine in the Yukon Territory since 2005. Work began by mobilizing to site on the winter road, establishing the decline portal, and excavating 1,200 metres of ramp, ore drift, and exploration drift for bulk sampling. Ongoing work will include continuation of main ramp development and lateral ore development for preproduction in preparation for mine start-up. Post preproduction will continue with production mining at a rate of 1,750 tonnes per day.
Location