projects > Bellekeno Development & Production Mining Project

Bellekeno Development & Production Mining Project

Alexco Keno Hill Mining Corp.
YUKON TERRITORY
START-UP: May 2008
COMPLETION: ongoing
RESOURCE:

Lat 63° 54’ N – Long 135° 15’ W

RESOURCE: Silver/Lead/Zinc

Located in the Keno Hill Mining District in the Yukon Territory, the NNDDC / Procon Joint Venture has been contracted for the underground development and rehabilitation at Alexco’s Bellekeno mine. This involves driving a 637m primary ramp, driving 160m of auxiliary development, driving 400m off the main ramp for additional infrastructure and diamond drill platforms, rehabbing the previously driven track and rail, and rehabbing the historical ramps for diamond drill stations. Procon is familiar with the Bellekeno property, having done some dewatering and rehab work in 1994 and 1,500' of new ramp development and 15,000' of diamond drilling in 1995.

Location
Road in to Bellekeno