Projects

Current Projects

 

Tyson Creek Hydro Project
K2 Mine Brine Inflow Project
Seymour-Capilano Twin Tunnels Project
Bellekeno Mine

Bingo Mine
Wolverine Project
Ekati Diamond Mine
Snap Lake Diamond Mine

Past Projects

 
Tulsequah Chief Project
Kumtor Mine
Nalunaq Gold Mine
Ruddock Creek Project
QR Project
Coeur and Galena Mines Project
Eskay Creek Project

Prairie Creek Project
Colonsay Mine

Rocanville Mine
Nico Bulk Sample Program
Allan Mine
Holloway-Holt Mine Projects

Nixon Fork Mine Project
Lanigan Mine
Malmbjerg Project
Davidson Project

Afton Copper-Gold Project
Ulu Mine Project
Cory Mine
Pogo Project
Tara Mine
Upper Mamquam Hydro Project
Brittania Mine
Boston Gold Project
McArthur River Mine
Myra Falls, Lynx Mine
Kodiak B Project
Dominique-Janine Project
McClean Lake Project
Giant Mine
Cigar Lake Mine
Komis Deposit
Goldstream Mine

 

Current Projects

Tyson Creek Hydro Project
Renewable Power Corp.

 

Start-up:

September 2008
The Tyson Creek Hydro Tunnel project is located in Narrows Inlet, about a one hour boat ride north of Sechelt, British Columbia. The Owner is currently constructing a hydro project to sell power to the BC Hydro grid. The tunnel will be driven about 400 meters in length at a grade of +/-12%. The tunnel will be driven this year and Procon will be back to do some mechanical installations and a lake tap in May 2009.
       

K2 Mine Brine Inflow Project
Mosaic Potash Esterhazy LP

 

Start-up:

July 2008
Work began on the Underground Brine Inflow and Surface Backfill Operations at the K2 Mine in Esterhazy, Saskatchewan in June 2008. Procon supplies the necessary labour, supervision, and related services to catch all current and new inflows, grout and backfill all caverns caused by washout and inflow dissolution, and provides ground support and control to existing and new excavations.
       

Seymour-Capilano Twin Tunnels Project
Metro Vancouver

 

Start-up:

May 2008
Procon is currently handling the monitoring/maintenance of the tunnels dewatering system and ventilation system at the Seymour-Capilano Twin Tunnels Project in Vancouver, British Columbia. The Seymour and Capilano watersheds supply up to 70% of the Lower Mainland’s drinking water. Construction of new water supply and treatment facilities for these water sources is underway in the Lower Seymour Conservation Reserve (LSCR) and at Capilano River Regional Park. Water from the Capilano Reservoir will be pumped through a 3.7-metre-diameter tunnel to the filtration plant in the LSCR. From here, the water will be filtered and disinfected, and returned to Capilano by gravity through a parallel tunnel of the same size. The twin tunnels will be approximately 7.1 kilometres long and 160-640 metres underground.
       

Bellekeno Mine
Alexco Resources Corp.

 

Start-up:

May 2008
Located in the Keno Hill Mining District in the Yukon Territory, Procon has been contracted for the underground development and rehabilitation at Alexco’s Bellekeno silver mine. This involves driving a 637m primary ramp, driving 160m of auxiliary development, driving 400m off the main ramp for additional infrastructure and diamond drill platforms, rehabbing the previously driven track and rail, and rehabbing the historical ramps for diamond drill stations. Procon is familiar with the Bellekeno property, having done some dewatering and rehab work in 1994 and 1,500' of new ramp development and 15,000' of diamond drilling in 1995.
       

Bingo Mine
Golden Band Resources Inc.

 

Start-up:

October 2007
Procon, with our joint venture partner Kitsaki, have begun work on the Bingo Exploration Decline Project in Northern Saskatchewan. This is a greenfield site, requiring construction of all access and infrastructure. The main concentration shall be on establishing a portal boxcut and developing 450m of decline and 130m x-cut in the ore. Kitsaki / Procon is providing all of the supervision, labour, materials, equipment, tools and services.
       

Wolverine Project
Yukon Zinc Corporation

 

Start-up:

March 2005
Procon has been at the Wolverine Mine in the Yukon Territory since 2005. Work has included mobilizing to site on the winter road, establishing the decline portal, and excavating 1,200 metres of ramp, ore drift, and exploration drift for diamond drilling.
       

Ekati Diamond Mine
BHP Billiton Diamonds Inc.

 

Start-up:

September 2000
Procon, along with our joint venture partner KeTe Whii Ltd., have been at the Ekati Mine in the Northwest Territories since 2000. Work started with the development of the Koala North Mine and has continued with the underground development of the Panda and Koala Mines. The Ekati Mine Site is deep in Canada’s far north so working conditions can be harsh, including driving ramps and levels in permafrost. KeTe Whii / Procon provide development and production personnel as well as equipment at the multi-mine site.
       

Snap Lake Diamond Mine
De Beers Canada Mining Inc.

 

Start-up:

February 2000
The Snap Lake Project is another KeTe Whii / Procon Joint Venture undertaking. Phase I pre-production began in 2000 with extending existing workings into the ore zone and has evolved into Phase 2 construction of the underground ore handling system and mine services. Phase 2 consists of over 9,000 meters of lateral development including excavations for the crusher, conveyor way, bins and pump stations. A joint venture has been formed with MONAD for the mechanical and electrical installation of the conveyors, crusher, feeders, dewatering system, and heating / ventilation plants for the mine.
       

Past Projects

Tulsequah Chief Project
Redfern Resources Corp.

 

Start-up:
Completion:

August 2008
January 2009
A base metal mine on the Tulsequah River, Tulsequah Chief is located 100 kilometers south of Atlin in northwestern British Columbia, but is actually closer to Juneau, Alaska, 64 kilometers southwest. Work on this project will consist of cleanup of existing adits, slashing existing adits for new mine access, and development of the main ramp and production levels.
 
       

Kumtor Mine
Kumtor Operating Company, CJSC

 

Start-up:
Completion:

October 2007
March 2009
Procon has been contracted to develop approximately 2,500 metres of underground exploration decline under an existing open pit in a remote location at a 4,000 metre elevation in the Tien Shan Mountains of Kyrgyzstan in Central Asia. Work will be completed using expatriate labour who will in turn train local national labour in the necessary mining skills.
       

Nalunaq Gold Mine
Crew Gold Corp.

 

Start-up:
Completion:

April 2000
February 2009
Located on the southern tip of Greenland, Procon began work at the Nalunaq Mine in 2000. Nalunaq is the first gold mine to be developed in Greenland and is the first mine to be put into production in Greenland in over 30 years. Crew access to this site is by plane or boat only, with equipment and supplies being brought in by ocean liners equipped with ice breakers. Procon supplies personnel and equipment for lateral development and production mining as well as Alimak raise crews.
       

Ruddock Creek Project
Selkirk Metals Corp.

 

Start-up:
Completion:

August 2007
November 2008
Procon began work on the Underground Development and Drilling Program at the Ruddock Creek Property in August of 2007. This is a greenfield site in Northeastern British Columbia which will require construction of a camp, access roads and portal. The development work will consist of 1,800m of underground exploration decline.
       

QR Project
Cross Lake Minerals Ltd.

 

Start-up:
Completion:

July 2007
February 2009

Another project in northeastern British Columbia, Procon began work at QR in July of 2007.

This is Procon’s second visit to this site having collared a 4 x 5 metre decline, drove 400 metres of decline from surface, drove 600 metres of drift, x-cut to obtain a bulk sample, and drove a 65 metre vent raise to surface in 1996.

       

Coeur and Galena Mines Project
U.S. Silver Idaho Inc.

 

Start-up:
Completion:

April 2007
October 2008
Procon’s U.S. Division has begun work at the Coeur and Galena Silver Mines in Wallace, Idaho. This project includes the underground rehabilitation of the 3700 Level and Galena Shaft.
       

Eskay Creek Project
Barrick Gold Corp.

 

Start-up:
Completion:

September 1992
September 2008
Northern British Columbia
  • 10,000 metres per annum of ore drifting in very poor ground conditions
  • Placement of cemented gravel fill to allow both overhand and underhand mining methods
  • 2,000 metres per annum of associated waste development
  • Associated underground construction as required
  • Contract mining 600-700 tonnes per day
  • Build diversion dam (conc. bag) on surface
  • Scale and bolt underground workings as part of ongoing rehabilitation
  • Rehabilitate caved section of underground workings
  • Drill, blast and bag bulk sample for testing purposes
  • Rehab main haulage way as part of mine preparation
  • Shop, sumps and other miscellaneous excavations as required for mine start-up
  • 3,000 metres of ramp and lateral development plus test mining of 10 - 20,000 tonnes
       

Prairie Creek Project
Canadian Zinc Corp.

 

Start-up:
Completion:

May 2004
September 2008
Northwest Territories
  • Work with Owner to get project up and running, including camp, equipment repairs, planning and engineering
  • Mobilize by fixed wing aircraft
  • Collar decline and drive 600 metres of 3.0x2.4m exploration decline at -15% gradient to provide a staging for deep drilling purposes
  • Provide support for diamond drilling
  • Operate and maintain camp
       

Colonsay Mine
Mosaic Potash ULC

 

Start-up:
Completion:

2007
2008
Northern Saskatchewan
  • Underground Conveyor Discharge Replacement
       

Rocanville Mine
Potash Corporation of Saskatchewan

 

Start-up:
Completion:

2007
2008
Northern Saskatchewan
  • Replacement of Manway Shaft Steel
     
^ top
       

Nico Bulk Sample Program
Fortune Minerals Ltd.

 

Start-up:
Completion:

2005
May 2008
Northwest Territories
  • Full mobilization of equipment, fuel, fuel tanks, truck shop, and offices
  • 1,711m ramp development and ore crosscut
  • 250 tonne bulk sample
  • 163m Alimak vent raise
     

Allan Mine
Potash Corporation of Saskatchewan

 

Start-up:
Completion:

2000
2007
Northern Saskatchewan
  • Service Shaft Steel Replacement
  • Loading Pocket Installation
  • U/G Hoist Upgrade Steel Modifications and Related Work
  • Installation of Chicklet Compactor including materials handling equipment
  • Installation of an Underground Storage Bin
  • Demolition and Construction of Potash Station Shaft Platform
       

Holloway-Holt Mine Projects
St. Andrew Goldfields Ltd.

 

Start-up:
Completion:

June 2007
October 2007
Timmins, Ontario
  • Mine development and longhole mine production
  • Extend existing workings into ore zones
  • 2,000 ore tpd planned production
       

Nixon Fork Mine Project
Mystery Creek Resources Inc.
(subsidiary of St Andrew Goldfields Ltd.)

 

Start-up:
Completion:

April 2007
September 2007
Central Alaska
  • Underground mine development and production of 250 tpd gold mine
       

Lanigan Mine
Potash Corporation of Saskatchewan

 

Start-up:
Completion:

2001
2007
Northern Saskatchewan
  • Replace Silo Bin Tripper System
  • U/G Skip Measurement Bin Modifications
  • U/G Bin Foundation Replacement
  • Service Station Upgrade
     
^ top
       

Malmbjerg Project
International Molybdenum/Quadra Mining

 

Start-up:
Completion:

Marc 2005
August 2007
Greenland
  • Mobilized by air and sea to Akureyai, Iceland, then to Mesters Vig, Greenland by large transport aircraft. From Mester Vig mobilization was completed by helicopter
  • Open 3 existing portals and rehabilitate some 1,700 metres of adit on 3 levels
  • Make underground workings safe and provide support for diamond drillers
       

Davidson Project
Blue Pearl Mining

 

Start-up:
Completion:

August 2005
May 2007
Smithers, British Columbia
  • Mobilize gensets and compressor to site to rehab existing workings (3.0kms)
  • Reestablish portal and 24" gauge rail, ventilation and services Provide electrical support during the underground diamond drilling phase
  • Develop 175m of tracked drift
       

Afton Copper-Gold Project
New Gold Inc.

 

Start-up:
Completion:

November 2004
December 2006
Kamloops, British Columbia
  • Setup and established new portal in existing pit wall
  • Excavate approximately 1,400 metres of decline and 600 metres of development off ramp, including 350 metres test drifting in ore
       

Ulu Mine Project
Wolfden Resources Inc.

 

Start-up:
Completion:

May 2006
August 2006
Nunavut
  • Ramp rehabilitation and ice removal
  • Rehab of Owner's equipment
       

Cory Mine
Potash Corporation of Saskatchewan

 

Start-up:
Completion:

2002
2005
Northern Saskatchewan
  • U/G Shaft Tower Rehabilitation
  • Scaling, rockbolting and general mine rehabilitation
       

Pogo Project
Teck Cominco

 

Start-up:
Completion:

January 1998
September 2005
Delta Junction, Alaska
  • Mobilize complete mining plant and supplies over winter road
  • Surface set-up including electrical distribution system, camp, septic system, roads and airstrip construction
  • Establish collar through overburden - install multi-plate portal structure
  • Drive 7,500' of 11' x 18' ramp for main access to ore body
  • Installation of an Underground Waste Water Treatment Plant (150 GPM)
     
^ top
       

Tara Mine
Boliden Tara Mines Ltd.

 

Start-up:
Completion:

June 1998
June 2005
Navan, Ireland
  • Provide mining crews for priority ramp and heading development
  • Alimak raising
  • Training of local crews
  • Provide expertise to improve mine development productivities

       

Upper Mamquam Hydro Project
Canadian Hydro Developers

 

Start-up:
Completion:

April 2004
October 2004
Squamish, British Columbia
  • Collar tunnel and drive 125 metres of 4x4m tunnel to break through rock bluff for penstock pipe installation
       

Brittania Mine
Golder Associates/Government of British Columbia

 

Start-up:
Completion:

December 2001
January 2002
Brittania Beach, British Columbia
  • Rehabilitation of 4100 Level adit to enable core sampling of concrete plug 400 metres from portal
       

Boston Gold Project
BHP Minerals Canada

 

Start-up:
Completion:

February 1996
September 2001
Spyder Lake, Nunavut
  • Establish portal and drive 360 metres of decline in permafrost conditions
  • Drive 600 metres of drift and x-cut to obtain underground bulk sample
  • Ramp extension and miscellaneous drifting totaling 1,000 metres
  • Diamond drill support and station excavation
  • Mobilize men, equipment and supplies via Hercules aircraft
  • Extend decline 900 metres, plus additional 1,000 metres of development, all in permafrost conditions
  • Construct airstrip utilizing waste rock
  • Mine and crush 25,000 tonne bulk sample
       

McArthur River Mine
Cameco Corp.

 

Start-up:
Completion:

1999
2001
Northern Saskatchewan
  • Install #3 Mine Air Heater Level 530 Freeze System Expansion
  • Erection of 33,000 sq. ft. Administration Building
  • Primary Water Treatment Plant
    • Demolition of equipment, tanks, steel concrete ductwork, piping, electrical and instrumentation in the existing plant to accommodate the new facilities
    • Concrete foundations, floor slab, sump, and pads
    • Steel platforms and support steel including relocation of existing stairs
    • Process equipment including Lamilla clarifier, mixing tanks agitators, pumps and ancillaries
    • HVAC and services equipment including make-up air, unit heaters, ductwork, safety shower/eyewash station and fire protection system
    • Piping systems for slurry, contaminated water, reagents, fresh water, fire water, plant air, and propane for the new primary water treatment and secondary water treatment piping systems
    • Electrical water supply and distribution equipment including MCC's, panels, cable trays, grounding, lighting, cabling, wiring and accessories
    • Field instruments and control valves, instrument junction boxes, cabling, wiring and accessories
     
^ top
       

Myra Falls, Lynx Mine
Boliden Westmin

 

Start-up:
Completion:

February 1996
December 2000
Vancouver Island, British Columbia
  • Provide supervision for track drift exploration program
  • Drift rehabilitation and timbering old workings

       

Kodiak B Project
Northern American Metals

 

Start-up:
Completion:

February 2000
October 2000
Golden Bear Mine, Dease Lake, British Columbia
  • Collar decline and drive 700 metres
  • Excavate 1,500 metres of level drifting opening 5 levels
  • Excavate 250 metres of various size slot and ventilation raises
  • Mine 250,000 tonnes of ore by longhole methods
  • Install ground support including 6,300 metres of grouted cable bolts in stope hanging walls
       

Dominique-Janine Project
Cogema Resources Inc.

 

Start-up:
Completion:

March 1996
May 1999
Cluff Lake, Northern Saskatchewan
  • Excavate 900 metres of 4.3 x 4.5 metre decline
  • Excavate 300 metres of 3.8 x 2.5 metre incline
  • Ongoing development and underhand cut and fill mining at 100 to 300 tonnes per day

       

McClean Lake Project
Cogema Resources Inc.

 

Start-up:
Completion:

August 1998
September 1998
Northern Saskatchewan
  • Drive 200 metres of 2.4 x 2.4 metre drainage adit and backfill with drainage gravel for the JEB Pit Tailings projects
  • Complete 1,500 metres of fully cased dewatering wells from 8" diameter to 16" diameter
     
^ top
       

Giant Mine
Royal Oak Mines Inc.

 

Start-up:
Completion:

May 1992
September 1998
Yellowknife, Northwest Territories
  • Grouting and ground support program Grout storage chambers
  • Construction of Main Haulage System\
  • 10,000' of drift slashing
  • Installation of trolley system
  • Installation of 85 lb. main haulage rail
  • Installation of the automated inline chute system
  • Installation of the main ore pass dump
  • Driving of 3,000' of Alimak ore pass, waste pass and ventilation raises
  • Dewater and rehabilitation of shaft
  • 4,000' of ramp development
  • 20,000 tons of mechanized cut and fill stoping
       

Cigar Lake Mine
Cameco Corporation

 

Start-up:
Completion:

June 1997
March 1998
Northern Saskatchewan
  • Install skip load-out system including all associated head frame modification
  • Construct ore storage bin c/w transfers and shaft skip pocket systems
  • Construct MDS assembly area c/w overhead crane installation
  • Lower and assemble the mechanized tunnel boring machine
  • Complete the initial MDS test mining including the installation of the precast lining segments
  • Complete 1,000 metres of jumbo development
       

Komis Deposit
Waddy Lake Resources Inc.

 

Start-up:
Completion:

October 1993
March 1997
La Ronge, Saskatchewan
  • Production of 400 tonnes per day using a combination of shrinkage and longhole mining methods
  • Completion of 6,000 metres of jumbo development
  • Completion of 1,000 metres of conventional raise development
  • Mobilize, set-up and collar adit
  • Drive first 100 metres of 3.5 x 5 metre decline at -15% gradient
  • Excavation of an additional 350 metres of 3.5 x 5 metre decline at -15% gradient
  • Excavation of 650 metres of 3.0 x 4.0 metre development on 2 levels
  • 90 metres of 1.5 x 2.1 metre ventilation raise
  • Extraction of a 10,000 tonne bulk ore sample
       

Goldstream Mine
Bethlehem Resources Corp.

 

Start-up:
Completion:

May 1993
February 1996
Revelstoke, British Columbia
  • Ore production ranging from 1,100 to 1,350 tonnes per day using a modified room and pillar longhole mining method
  • Total jumbo development of 21,000 metres
  • Conventional raising of 1,500 metres
  • A single pass 400 metre Alimak ventilation raise

     
^ top
       

 

 

 
 