Tulsequah Chief Project
Redfern Resources Corp. |
|
Start-up:
Completion: |
August 2008
January 2009 |
| A base metal mine on the Tulsequah River, Tulsequah Chief is located 100 kilometers south of Atlin in northwestern British Columbia, but is actually closer to Juneau, Alaska, 64 kilometers southwest. Work on this project will consist of cleanup of existing adits, slashing existing adits for new mine access, and development of the main ramp and production levels. |
| |
| |
|
|
|
Kumtor Mine
Kumtor Operating Company, CJSC |
|
Start-up:
Completion: |
October 2007
March 2009 |
| Procon has been contracted to develop approximately 2,500 metres of underground exploration decline under an existing open pit in a remote location at a 4,000 metre elevation in the Tien Shan Mountains of Kyrgyzstan in Central Asia. Work will be completed using expatriate labour who will in turn train local national labour in the necessary mining skills. |
| |
|
|
|
Nalunaq Gold Mine
Crew Gold Corp. |
|
Start-up:
Completion: |
April 2000
February 2009 |
| Located on the southern tip of Greenland, Procon began work at the Nalunaq Mine in 2000. Nalunaq is the first gold mine to be developed in Greenland and is the first mine to be put into production in Greenland in over 30 years. Crew access to this site is by plane or boat only, with equipment and supplies being brought in by ocean liners equipped with ice breakers. Procon supplies personnel and equipment for lateral development and production mining as well as Alimak raise crews. |
| |
|
|
|
Ruddock Creek Project
Selkirk Metals Corp. |
|
Start-up:
Completion: |
August 2007
November 2008 |
| Procon began work on the Underground Development and Drilling Program at the Ruddock Creek Property in August of 2007. This is a greenfield site in Northeastern British Columbia which will require construction of a camp, access roads and portal. The development work will consist of 1,800m of underground exploration decline. |
| |
|
|
|
QR Project
Cross Lake Minerals Ltd. |
|
Start-up:
Completion: |
July 2007
February 2009 |
Another project in northeastern British Columbia, Procon began work at QR in July of 2007.
This is Procon’s second visit to this site having collared a 4 x 5 metre decline, drove 400 metres of decline from surface, drove 600 metres of drift, x-cut to obtain a bulk sample, and drove a 65 metre vent raise to surface in 1996.
|
| |
|
|
|
Coeur and Galena Mines Project
U.S. Silver Idaho Inc. |
|
Start-up:
Completion: |
April 2007
October 2008 |
| Procon’s U.S. Division has begun work at the Coeur and Galena Silver Mines in Wallace, Idaho. This project includes the underground rehabilitation of the 3700 Level and Galena Shaft. |
| |
|
|
|
Eskay Creek Project
Barrick Gold Corp. |
|
Start-up:
Completion: |
September 1992
September 2008 |
Northern British Columbia
- 10,000 metres per annum of ore drifting in very poor ground conditions
- Placement of cemented gravel fill to allow both overhand and underhand mining methods
- 2,000 metres per annum of associated waste development
- Associated underground construction as required
- Contract mining 600-700 tonnes per day
- Build diversion dam (conc. bag) on surface
- Scale and bolt underground workings as part of ongoing rehabilitation
- Rehabilitate caved section of underground workings
- Drill, blast and bag bulk sample for testing purposes
- Rehab main haulage way as part of mine preparation
- Shop, sumps and other miscellaneous excavations as required for mine start-up
- 3,000 metres of ramp and lateral development plus test mining of 10 - 20,000 tonnes
|
| |
|
|
|
Prairie Creek Project
Canadian Zinc Corp. |
|
Start-up:
Completion: |
May 2004
September 2008 |
Northwest Territories
- Work with Owner to get project up and running, including camp, equipment repairs, planning and engineering
- Mobilize by fixed wing aircraft
- Collar decline and drive 600 metres of 3.0x2.4m exploration decline at -15% gradient to provide a staging for deep drilling purposes
- Provide support for diamond drilling
- Operate and maintain camp
|
| |
|
|
|
Colonsay Mine
Mosaic Potash ULC |
|
Start-up:
Completion: |
2007
2008 |
Northern Saskatchewan
- Underground Conveyor Discharge Replacement
|
| |
|
|
|
Rocanville Mine
Potash Corporation of Saskatchewan |
|
Start-up:
Completion: |
2007
2008 |
Northern Saskatchewan
- Replacement of Manway Shaft Steel
|
| |
|
|
|
| |
|
|
|
Nico Bulk Sample Program
Fortune Minerals Ltd. |
|
Start-up:
Completion: |
2005
May 2008 |
Northwest Territories
- Full mobilization of equipment, fuel, fuel tanks, truck shop, and offices
- 1,711m ramp development and ore crosscut
- 250 tonne bulk sample
- 163m Alimak vent raise
|
| |
|
|
|
Allan Mine
Potash Corporation of Saskatchewan |
|
Start-up:
Completion: |
2000
2007 |
Northern Saskatchewan
- Service Shaft Steel Replacement
- Loading Pocket Installation
- U/G Hoist Upgrade Steel Modifications and Related Work
- Installation of Chicklet Compactor including materials handling equipment
- Installation of an Underground Storage Bin
- Demolition and Construction of Potash Station Shaft Platform
|
| |
|
|
|
Holloway-Holt Mine Projects
St. Andrew Goldfields Ltd. |
|
Start-up:
Completion: |
June 2007
October 2007 |
Timmins, Ontario
- Mine development and longhole mine production
- Extend existing workings into ore zones
- 2,000 ore tpd planned production
|
| |
|
|
|
Nixon Fork Mine Project
Mystery Creek Resources Inc.
(subsidiary of St Andrew Goldfields Ltd.) |
|
Start-up:
Completion: |
April 2007
September 2007 |
Central Alaska
- Underground mine development and production of 250 tpd gold mine
|
| |
|
|
|
Lanigan Mine
Potash Corporation of Saskatchewan |
|
Start-up:
Completion: |
2001
2007 |
Northern Saskatchewan
- Replace Silo Bin Tripper System
- U/G Skip Measurement Bin Modifications
- U/G Bin Foundation Replacement
- Service Station Upgrade
|
| |
|
|
|
| |
|
|
|
Malmbjerg Project
International Molybdenum/Quadra Mining |
|
Start-up:
Completion: |
Marc 2005
August 2007 |
Greenland
- Mobilized by air and sea to Akureyai, Iceland, then to Mesters Vig, Greenland by large transport aircraft. From Mester Vig mobilization was completed by helicopter
- Open 3 existing portals and rehabilitate some 1,700 metres of adit on 3 levels
- Make underground workings safe and provide support for diamond drillers
|
| |
|
|
|
Davidson Project
Blue Pearl Mining |
|
Start-up:
Completion: |
August 2005
May 2007 |
Smithers, British Columbia
- Mobilize gensets and compressor to site to rehab existing workings (3.0kms)
- Reestablish portal and 24" gauge rail, ventilation and services Provide electrical support during the underground diamond drilling phase
- Develop 175m of tracked drift
|
| |
|
|
|
Afton Copper-Gold Project
New Gold Inc. |
|
Start-up:
Completion: |
November 2004
December 2006 |
Kamloops, British Columbia
- Setup and established new portal in existing pit wall
- Excavate approximately 1,400 metres of decline and 600 metres of development off ramp, including 350 metres test drifting in ore
|
| |
|
|
|
Ulu Mine Project
Wolfden Resources Inc. |
|
Start-up:
Completion: |
May 2006
August 2006 |
Nunavut
- Ramp rehabilitation and ice removal
- Rehab of Owner's equipment
|
| |
|
|
|
Cory Mine
Potash Corporation of Saskatchewan |
|
Start-up:
Completion: |
2002
2005 |
Northern Saskatchewan
- U/G Shaft Tower Rehabilitation
- Scaling, rockbolting and general mine rehabilitation
|
| |
|
|
|
Pogo Project
Teck Cominco |
|
Start-up:
Completion: |
January 1998
September 2005 |
Delta Junction, Alaska
- Mobilize complete mining plant and supplies over winter road
- Surface set-up including electrical distribution system, camp, septic system, roads and airstrip construction
- Establish collar through overburden - install multi-plate portal structure
- Drive 7,500' of 11' x 18' ramp for main access to ore body
- Installation of an Underground Waste Water Treatment Plant (150 GPM)
|
| |
|
|
|
| |
|
|
|
Tara Mine
Boliden Tara Mines Ltd. |
|
Start-up:
Completion: |
June 1998
June 2005 |
Navan, Ireland
- Provide mining crews for priority ramp and heading development
- Alimak raising
- Training of local crews
- Provide expertise to improve mine development productivities
|
| |
|
|
|
Upper Mamquam Hydro Project
Canadian Hydro Developers |
|
Start-up:
Completion: |
April 2004
October 2004 |
Squamish, British Columbia
- Collar tunnel and drive 125 metres of 4x4m tunnel to break through rock bluff for penstock pipe installation
|
| |
|
|
|
Brittania Mine
Golder Associates/Government of British Columbia |
|
Start-up:
Completion: |
December 2001
January 2002 |
Brittania Beach, British Columbia
- Rehabilitation of 4100 Level adit to enable core sampling of concrete plug 400 metres from portal
|
| |
|
|
|
Boston Gold Project
BHP Minerals Canada |
|
Start-up:
Completion: |
February 1996
September 2001 |
Spyder Lake, Nunavut
- Establish portal and drive 360 metres of decline in permafrost conditions
- Drive 600 metres of drift and x-cut to obtain underground bulk sample
- Ramp extension and miscellaneous drifting totaling 1,000 metres
- Diamond drill support and station excavation
- Mobilize men, equipment and supplies via Hercules aircraft
- Extend decline 900 metres, plus additional 1,000 metres of development, all in permafrost conditions
- Construct airstrip utilizing waste rock
- Mine and crush 25,000 tonne bulk sample
|
| |
|
|
|
McArthur River Mine
Cameco Corp. |
|
Start-up:
Completion: |
1999
2001 |
Northern Saskatchewan
- Install #3 Mine Air Heater Level 530 Freeze System Expansion
- Erection of 33,000 sq. ft. Administration Building
- Primary Water Treatment Plant
- Demolition of equipment, tanks, steel concrete ductwork, piping, electrical and instrumentation in the existing plant to accommodate the new facilities
- Concrete foundations, floor slab, sump, and pads
- Steel platforms and support steel including relocation of existing stairs
- Process equipment including Lamilla clarifier, mixing tanks agitators, pumps and ancillaries
- HVAC and services equipment including make-up air, unit heaters, ductwork, safety shower/eyewash station and fire protection system
- Piping systems for slurry, contaminated water, reagents, fresh water, fire water, plant air, and propane for the new primary water treatment and secondary water treatment piping systems
- Electrical water supply and distribution equipment including MCC's, panels, cable trays, grounding, lighting, cabling, wiring and accessories
- Field instruments and control valves, instrument junction boxes, cabling, wiring and accessories
|
| |
|
|
|
| |
|
|
|
Myra Falls, Lynx Mine
Boliden Westmin |
|
Start-up:
Completion: |
February 1996
December 2000 |
Vancouver Island, British Columbia
- Provide supervision for track drift exploration program
- Drift rehabilitation and timbering old workings
|
| |
|
|
|
Kodiak B Project
Northern American Metals |
|
Start-up:
Completion: |
February 2000
October 2000 |
Golden Bear Mine, Dease Lake, British Columbia
- Collar decline and drive 700 metres
- Excavate 1,500 metres of level drifting opening 5 levels
- Excavate 250 metres of various size slot and ventilation raises
- Mine 250,000 tonnes of ore by longhole methods
- Install ground support including 6,300 metres of grouted cable bolts in stope hanging walls
|
| |
|
|
|
Dominique-Janine Project
Cogema Resources Inc. |
|
Start-up:
Completion: |
March 1996
May 1999 |
Cluff Lake, Northern Saskatchewan
- Excavate 900 metres of 4.3 x 4.5 metre decline
- Excavate 300 metres of 3.8 x 2.5 metre incline
- Ongoing development and underhand cut and fill mining at 100 to 300 tonnes per day
|
| |
|
|
|
McClean Lake Project
Cogema Resources Inc. |
|
Start-up:
Completion: |
August 1998
September 1998 |
Northern Saskatchewan
- Drive 200 metres of 2.4 x 2.4 metre drainage adit and backfill with drainage gravel for the JEB Pit Tailings projects
- Complete 1,500 metres of fully cased dewatering wells from 8" diameter to 16" diameter
|
| |
|
|
|
| |
|
|
|
Giant Mine
Royal Oak Mines Inc. |
|
Start-up:
Completion: |
May 1992
September 1998 |
Yellowknife, Northwest Territories
- Grouting and ground support program Grout storage chambers
- Construction of Main Haulage System\
- 10,000' of drift slashing
- Installation of trolley system
- Installation of 85 lb. main haulage rail
- Installation of the automated inline chute system
- Installation of the main ore pass dump
- Driving of 3,000' of Alimak ore pass, waste pass and ventilation raises
- Dewater and rehabilitation of shaft
- 4,000' of ramp development
- 20,000 tons of mechanized cut and fill stoping
|
| |
|
|
|
Cigar Lake Mine
Cameco Corporation |
|
Start-up:
Completion: |
June 1997
March 1998 |
Northern Saskatchewan
- Install skip load-out system including all associated head frame modification
- Construct ore storage bin c/w transfers and shaft skip pocket systems
- Construct MDS assembly area c/w overhead crane installation
- Lower and assemble the mechanized tunnel boring machine
- Complete the initial MDS test mining including the installation of the precast lining segments
- Complete 1,000 metres of jumbo development
|
| |
|
|
|
Komis Deposit
Waddy Lake Resources Inc. |
|
Start-up:
Completion: |
October 1993
March 1997 |
La Ronge, Saskatchewan
- Production of 400 tonnes per day using a combination of shrinkage and longhole mining methods
- Completion of 6,000 metres of jumbo development
- Completion of 1,000 metres of conventional raise development
- Mobilize, set-up and collar adit
- Drive first 100 metres of 3.5 x 5 metre decline at -15% gradient
- Excavation of an additional 350 metres of 3.5 x 5 metre decline at -15% gradient
- Excavation of 650 metres of 3.0 x 4.0 metre development on 2 levels
- 90 metres of 1.5 x 2.1 metre ventilation raise
- Extraction of a 10,000 tonne bulk ore sample
|
| |
|
|
|
Goldstream Mine
Bethlehem Resources Corp. |
|
Start-up:
Completion: |
May 1993
February 1996 |
Revelstoke, British Columbia
- Ore production ranging from 1,100 to 1,350 tonnes per day using a modified room and pillar longhole mining method
- Total jumbo development of 21,000 metres
- Conventional raising of 1,500 metres
- A single pass 400 metre Alimak ventilation raise
|
| |
|
|
|
| |
|
|
|