Renewable Resources Corp.

The Tyson Creek Hydro Tunnel project was located in Narrows Inlet, about a one hour boat ride north of Sechelt, British Columbia. The Owner, Renewable Resources Corp is currently constructing a hydro project to sell power to the BC Hydro grid. Procon drove a tunnel about 400 meters in length at a grade of +/-12%. The tunnel was completed in 2008 then the mechanical installations and lake tap in 2009.

  • Location: Sunshine Coast, B.C.
  • Start-up: August 2008
  • Completion: November 2009
  • Resource: Renewable Energy