Bellekeno Development & Production Mining Project

Loading
Center map
Traffic
Bicycling
Transit
Google MapsGet Directions

Bellekeno Development & Production Mining Project

Alexco Keno Hill Mining Corp.

Located in the Keno Hill Mining District in the Yukon Territory, the NNDDC / Procon Joint Venture was contracted for the underground development and rehabilitation at Alexco’s Bellekeno mine. This involved driving a 637m primary ramp, driving 160m of auxiliary development, driving 400m off the main ramp for additional infrastructure and diamond drill platforms, rehabbing the previously driven track and rail, and rehabbing the historical ramps for diamond drill stations. Procon is familiar with the Bellekeno property, having done some dewatering and rehab work in 1994 and 1,500′ of new ramp development and 15,000′ of diamond drilling in 1995.

  • Location: Yukon Territory
  • Start-up: May 2008
  • Completion: September 2013
  • Resource: Silver/Lead/Zinc
  • Coordinates: Lat 63° 54’ N – Long 135° 15’ W
  • Joint Venture: NNDDC